Sample report / Detached ADU

A backyard home without giving up the house.

SE 55th Avenue · South Tabor, Portland

Site map

DWELLPILOT / SITE ATLASSE 55th AvenueSouth Tabor · Portland, OR
HouseADU study area
↑ N
Imagery: Multnomah County
LayersCode setbacks · always shown
Read the site Select the retained house or ADU study area to inspect it. Drag to pan; use + to zoom. Boundaries and setbacks are preliminary.

Open SE 55th 3D site map

See the before-and-after comparison

Could a one-bedroom home fit behind the existing house? This study tests an 800 sq ft detached accessory dwelling unit (ADU) on a narrow Portland lot.

Parent lot
5,120 sq ft
Mapped zone
R5
Modeled new home
800 sq ft
Homes after project
2
View full reportCompare paths, check code and explore the site records.

Study the rear yard first. The engine identifies space beyond the existing house while reserving 10 feet of separation. The shaded area is where to test a floor plan, not a proposed building footprint.

The estimate is for the modeled path on this property. It excludes the purchase price of the existing land and is not a contractor bid.

Development cost estimate

$282,000 project spend · planning estimate. Planning range $259,000 to $307,000.

Base engine scenario · 800 SF · 14 months. Open a phase for its scope and pricing basis. These are not tuner what-if figures.

Preconstruction and due diligence: $3,246

Survey, site investigation, geotechnical work, feasibility and consultant proposals

Preconstruction services allowance: $3,246 (allocated). Planning split: 20% of the remaining design/engineering/permit allowance after itemized charges. Replace with a scoped proposal.

Design and engineering: $12,982

Architectural, structural, civil and specialty design scope and proposal

Design and engineering services allowance: $12,982 (allocated). Planning split: remaining 80%; not a design proposal.

Permitting and plan review: $5,844

Authority, valuation, application count, trade permits and inspection schedule

Building, plan review, trade, site and PBOT review permits (1 × ~$5,844): $5,844 (itemized). Project: Every new dwelling. Building fee from valuation ($175/SF × 800 SF = $140,000); plan review 65%; 12% state surcharge on building and trade permits. Cost reference

Development charges and taxes: $2,928 · partly priced

District, use, units, meters, credits, waivers, plat and recording charges

Construction excise taxes (1 × ~$2,928): $2,928 (itemized). Project: Affordable housing CET 1% of valuation when it is $100k or more (ADUs included since 2018); Metro CET 0.12% above $100k; school CET ~$1.7/SF (district varies $1.63–1.70). Cost reference

ADU SDCs (1 ADU): conditional. Waived with a recorded 10-year covenant against short-term rental (water waiver capped at a 3/4" meter). ADUs are not covered by the temporary new-unit exemption. Conditional reference amount: $22,177; not added. Cost reference

Site work and utilities: $14,000

Demolition, grading, access, frontage, drainage and service quantities

Sewer/electrical service work + water sub-meter: $14,000 (modeled). Existing path budget; net of any amounts allocated above.

Building construction: $216,000

Structure type, area, units, assemblies, finish level, trade rates and bids

Construction (800 SF): $216,000 (modeled). Typical finishes at $375/SF for a 650 SF reference unit, scaled for size.

Construction contingency: $19,000

Risk scope and allowance basis

Contingency: $19,000 (modeled). Existing path budget; net of any amounts allocated above.

Financing and holding costs: $8,000 · partly priced

Draw schedule, rate, duration, loan fees, taxes and insurance during construction

Financing carry (7.5% for ~14 mo): $8,000 (modeled). Modeled interest on an assumed draw schedule; not a loan quote.

Other holding and financing expenses: to confirm. Property tax, insurance, lender fees and other non-interest holding costs are not separately priced. Verify coverage and monthly amounts.

Disposition and closing: not applicable

Exit strategy, sale price, commission and closing terms

Project spend excludes land. Land shown separately is the modeled land contribution, not a purchase or closing quote. Unpriced scope is not zero.

  • Survey the boundaries. Use the surveyed lot lines, not the fence, to verify setbacks before placing exterior walls.
  • Check the route to the rear. Measure the clear route beside the existing house for construction and fire access. Fire access remains a manual review item.
  • Confirm trees and services. Have an arborist review trees near the proposed work and verify the route and capacity of utility connections.

Read-only sample · DwellPilot engine 2.16.3 · November 2026. This is one development path, not a finding of permit approval or the highest-return option.